RPA is delighted to announce the opening of the Mater D-Wall Works Public Information Centre. Find out all you need to know on how the Mater D-Wall will be built on the Mater campus site.
The centre is located in RPA offices on Parkgate Street. Opening hours are Monday-Friday 9.00am - 5.00pm.

The Mater D-Wall is part of the future Mater Metro North stop. It is being built now to facilitate the opening of the Mater Adult Hospital which is planned for 2012.

The Mater D-Wall is an eighty metre long underground diaphragm wall (D-Wall) on the grounds of the Mater campus.
To find out more about the Mater D-Wall and how it will be built please click on the construction updates below.
Construction Update No. 1 - November 14, 2011
Construction Update No. 2 - December 20, 2011
Construction Update No. 3 - December 23, 2011
Construction Update No. 4 - January 12, 2012
Construction Update No. 5 - January 27, 2012
Construction Update No. 6 - February 03, 2012
Construction Update No. 7 - February 10, 2012
Construction Update No. 8 - February 18, 2012
Construction Update No. 9 - March 03, 2012
Construction Update No. 10 - March 13, 2012
Construction Update No. 11 - March 16, 2012
Construction Update No. 12 - April 02, 2012
Construction Update No. 13 - May 01, 2012
Construction Update No. 14 - May 11, 2012
Construction Update No. 15 - June 20, 2012
Construction Update No. 16 - July 18, 2012
BAM has been appointed to construct the D-Wall. Work is to start in January 2012 and last until July 2012.