Luas Liberties (Line F2)

Phase 5: Construction

At this phase, RPA contractors and sub-contractors will begin to physically construct the approved light rail line.  

Stage 1: Utility Diversions

The first stage of construction is the diversions of utilities; this means moving the pipes and cables where the Luas track is to be located.

Stage 2: Bridge Construction

Any structures such as bridges or underpasses need to be in place before the track construction starts. 

Stage 3: Track Construction

Once areas are prepared construction of the Luas track bed and the laying of the Luas tracks will start.

Stage 4: Stop Construction

Once the track bed is complete and the tracks have been laid the Luas stops are built. This can also happen at the same time as the track construction.

Stage 5: Electrical and Mechanical Works

Once the track and stops are built the next stage is the works involved in supplying power and necessary control systems to the line.

Stage 6: Testing and Commissioning

At this stage the Luas line in construction will look like a functioning Luas line but all systems have to be tested. From time to time you may see Luas trams on the line testing the systems.

Stage 7: Commencement of Operations

Once pre-operational safety testing is complete the line will be opened to the public and will form part of the extended Luas Red Line.

Construction works on Luas Lucan/Liberties will be carried-out based on the design drawings for the alignment and on an agreed schedule between RPA and its contractors.


To find out more about a particular phase or to view published information for this line, please click on one of the phases below. Identify Route OptionsRoute SelectionLine & Stop Design

Published Information

Re-sort Documents :
Webfeed Podcast

News

Luas fares to increase

Thursday, January 05, 2012

  Luas fares to increase by an average of 6.3% from Monday, 9th January 2012 RPA today announced Luas fare increases which will come into effect from Monday, 9th January 2012. There has...

...read more

Luas Pedestrians ACT SAFELY THINK SAFELY

Friday, September 30, 2011

Luas Pedestrians ACT SAFELY THINK SAFELY Luas today teamed up with the Gardai in a joint safety message to the public, in particular pedestrians. The Luas safety message is simple; Pedest...

...read more

Luas Park and Ride All Day Parking 4 Euro

Tuesday, August 09, 2011

Luas Park and Ride All Day Parking 4 Euro Did you know that you can park at any one of Luas’s Park and Ride car parks for just €4 all day and only €2 for up to 4 hours? The recent opening of t...

...read more

Search News Archive